The auto-scheduler constructs a plan using work item details which you can then adjust to meet your exact needs. To do this, it balances a range of different values from the dates assigned to a work item, work item estimates, a team’s capacity and velocity, and any dependencies between work items. There isn’t one aspect that the auto-scheduler focuses on, but rather takes all of them in aggregate.
However, one requirement for all work items is that they have a To Do or In Progress status. Work items with Done statuses are ignored by the auto-scheduler. Beyond this, you can select which work items you want the auto-scheduler to work on by selecting work items in the Scope column before using it. If you select none, the auto-scheduler works on your whole plan.
By default, the auto-scheduler schedules all work items in your plan, regardless of whether you’ve set dates for them. To exclude already-scheduled work items from the auto-scheduler, you’ll need to choose which work items it can overwrite. See how to configure the auto-scheduler.
これ以外にもさまざまな機能をご利用いただけます。このページでは、以下のトピックについてご説明します。
自動スケジューラーが日付を処理する仕組み
When scheduling work items, the auto-scheduler looks at the work item’s start and end date if there’s no estimation defined. If it has none, then the auto-scheduler looks for a sprint assignment, and assigns it those dates. If it has no sprint assignment or assigned dates, the auto-scheduler checks to see if it’s included in a release, and then assign the dates of the release.
自動スケジューラーがキャパシティを割り当てる仕組み
In order to allocate capacity, your work items need to have an estimate. Work items without estimates may still be scheduled according to dates, but won’t be included in capacity calculations.
自動スケジューラーは、スプリントのキャパシティを先着順で割り当てます。優先順位は次のとおりです。
work item rank as defined on your timeline
the auto-scheduler starts at the top of your plan and works its way down based on work item rankings; work items ranked higher are scheduled first. Read more about work item ranking.
a work item’s estimation
work items of lower hierarchy levels (stories or subtasks take priority over epics or initiatives)
for the reasons discussed below, we recommend that you only estimate work items at the story level, and that you show rolled-up values in your plan
これらの主要な要素以外にも、自動スケジューラーは他の計画データも考慮します。
Work source assignment
teams associated to a work source (board, project, or filter) are prioritized when assigning work
チームのベロシティ
チーム ベロシティが高いほど、1 回のスプリントでより多くの作業をこなせることを意味します
チーム メンバーの数
since the auto-scheduler assumes that one person can handle one story-level work item at a time, the number of team members affects how many work items can run in parallel
スプリント情報
スプリントの期間とキャパシティ
リリース
if this field is empty, the auto-scheduler assigns a work item to the next available release
依存関係
if two work items are dependent on each other (also known as a cyclical dependency), they’ll be ignored by the auto-scheduler; examples include:
work item A blocks work item B, and work item B blocks work item A
ストーリーが独自のサブタスクとの依存関係を持っている場合
自動スケジューラーがより高い階層レベルを処理する仕組み
As covered above, the auto-scheduler assumes that one person can work on one task when dealing with story-level work items. This isn’t the case when working with hierarchy levels above epic; if your plan includes an estimated work item at the epic-level or above, the auto-scheduler schedules the work item according to the team’s full capacity, as it assumes that everyone can work simultaneously on it.
If, in the example above, the work item that you estimated at 10 story points was an epic (instead of a story-level work item), the auto-scheduler would assign it one sprint instead of three.
To resolve this, we recommend that you only estimate work items at the story level, and that you show rolled-up values in your plan.
自動スケジューラーがアクティブ スプリントを処理する仕組み
これは、スプリントが予期せずオーバーブッキングされる一般的な要因となります。
自動スケジューラーは、今後予定されているスプリントとは異なる方法でアクティブ スプリントを処理します。
First of all, the auto-scheduler won’t reschedule work items in the active sprint, even if it’s overbooked.
Secondly, the auto-scheduler won’t overwrite any values of work items in the active sprint. Sprint, Team, and Release can only be overwritten in the active sprint if the field is empty. See how to configure the auto-scheduler.
自動スケジューラーがキャパシティを処理する仕組み
これは、スプリントが予期せずオーバーブッキングされる一般的な要因となります。
自動スケジューラーは、キャパシティ配分アルゴリズムに基づいてキャパシティを処理します。計画におけるキャパシティの配分方法の詳細をご確認ください。