タイムラインで依存関係を作成または削除する

This page is for software projects

To check whether you’re in a software or business project, select More actions (•••) next to the project name in either the header or the sidebar. At the bottom of the menu that opens, your project details will be shown.

You must have the following to do the things described on this page.

Permission: Link work items

Dependencies, also called Work item links in other parts of Jira, allow you to show the order in which work items need to be done. If there’s a dependency between two work items, one must be finished before the next can begin.

In order to use this feature, a Jira admin needs to enable work item linking. The timeline can only show work items with the Blocks work item link type and link work items from a single project. How to enable work item linking

Create a dependency

タイムラインに依存関係を直接作成するには、次の手順に従います。

  1. 作業項目のスケジュール バーにカーソルを合わせると、上の図のように両側にドットが表示されます。

  2. Drag one of the dots to the work item you want to link. The timeline automatically configures the order of the dependency (blocks or is blocked by) based on the order in which work items are scheduled.

Jira Software Cloud でプロジェクト ロードマップから依存関係を作成する

サイド作業項目ビュー パネルから依存関係を作成するには、次の手順に従います。

  1. Highlight a work item on the timeline to open the side info panel.

  2. Select the icon to open the link menu, then choose Link work item.

  3. [blocks (ブロックしている)] または [is blocked by (ブロックされている)] を選択してから、リンク先の作業項目を選択します。

依存関係の詳細を表示する

To view dependency details, select the line between dependent items.

依存関係を削除する

To remove a dependency between two work items:

  1. Select the line linking the work items you want to separate to open the the dependency view window.

  2. アイコンを選択して依存関係を削除します。