View and understand the cumulative flow diagram

This page is for company-managed projects

To check whether your project is team-managed or company-managed, select more actions (•••) next to the project name in either the header or the sidebar. At the bottom of the menu that opens, you’ll be able to view whether your project is team-managed or company-managed.

More about the difference between company-managed and team-managed projects.

A Cumulative Flow Diagram (CFD) is an area chart that shows the various statuses of work items for an application, version, or sprint. The horizontal x-axis in a CFD indicates time, and the vertical y-axis indicates cards (work items). Each colored area of the chart equates to a workflow status (i.e. a column on your board).

The CFD can be useful for identifying bottlenecks. If your chart contains an area that is widening vertically over time, the column that equates to the widening area will generally be a bottleneck.

Viewing the cumulative flow diagram

  1. Go to the project where your board is located, then select your board from the Board menu.

  2. Click Reports, then select Cumulative Flow Diagram.

    • To refine the data shown in the report, click Refine report, and select the desired filters.

    • To select a different timeframe, click the date range drop-down at the top of the chart.

    • To select a different date range, drag your cursor across the 'Overview' at the bottom of the chart.

Understanding the cumulative flow diagram

Before you start using the CFD, you should get to know how it works. The following information will help you understand its key functionalities:

  • The CFD is board-specific – that is, it will only include work items that match your board's saved filter.

  • It is based on your board's column mapping. A work item is considered to be 'To Do' when it is in a status that has been mapped to the left-most column of your board. Similarly, a work item is considered to be 'Done' when it is in a status that has been mapped to the right-most column of your board. Read more about configuring columns.

  • It keeps track of how many work items are passing through each column of your board, helping you see which columns accumulate more work items than others. 

For example: 

  1. If you start a sprint with 5 work items, they will begin in the To Do column. If you view the CFD, it will show 5 work items To Do, 0 work items In Progress, and 0 work items Done

  2. If you then move 2 work items to In Progress, the CFD will display 5 work items To Do (because 5 have passed through that column), 2 work items In Progress, and 0 work items Done

  3. If you then move 1 work item from In Progress to Done, the CFD will show To Do = 5, In Progress = 2, and Done = 1. 

  4. If you then take that 1 work item out of Done and move it back to To Do, the CFD will remove the 1 from Done and remove 1 from In Progress, but the numbers in To Do will remain the same, because no new work items have arrived. Therefore, the CFD will show To Do = 5, In Progress = 1, Done = 0.

 

Need help? If you can't find the answer you need in our documentation, we have other resources available to help you. See Getting help.