What are partial rollups in your plan?

This page refers to the advanced planning features that are only available as part of Jira Software Cloud Premium and Enterprise.

We have a separate section for documentation about the project timeline that’s included in all Jira Software projects. Go to the documentation for project-level roadmaps in Jira Software.

If your schedule bars have a striped pattern that fades out in one direction, this indicates that a parent issue is using one set date and one date rolled-up from child issues. This is called a partial roll-up, and is demonstrated below:

An example of a partial rollup date in Advanced Roadmaps for Jira Software Cloud

If a parent issue’s schedule bar fades out completely, it means that one date can’t be inferred since a child issue doesn't have a start and end date assigned to them. Missing start or end dates prevent your plan from determining a roll-up date, and so the schedule bar fades out.

An example of a partial roll up in Advanced Roadmaps for Jira Software Cloud.

To fix a partial roll-up, ensure that all child issues have start and end dates.