View and understand the epic report

This page applies to company-managed projects only.

Learn more about the difference between company-managed and team-managed projects.

Please note that epics can be renamed. The information in this article is relevant, regardless of what epics are called in your instance.

The epic report, which has a y-axis indicating story points and an x-axis indicating time.

The Epic Report shows a list of complete, incomplete, and unestimated issues in an epic. It is particularly useful in planning work for an epic that may extend over multiple sprints.

Use the Epic Report to understand the progress towards completing an epic over time, and to track the amount of remaining work that's incomplete or unestimated.

Before you begin

This page only applies to Scrum boards.

Viewing the Epic Report 

  1. Click Projects in the navigation bar and select the relevant project

  2. Click Reports then select Epic Report

  3. Select the relevant epic from the epic drop-down

  1. Click View in Issue Navigator to jump to the Issue Navigator and see a list of all the epic's issues.

Understanding the Epic Report

Before you start using the Epic Report, you should get to know how it works. The following information will help you understand the key functionalities of the Epic Report:

  • The Epic Report is based on your board's column mapping. An issue is considered to be 'To Do' when it is in a status that has been mapped to the left-most column of your board. Similarly, an issue is considered to be 'Done' when it is in a status that has been mapped to the right-most column of your board. See Configuring columns for more information.

  • The graph will look different if you are using Issue Count as your Estimation Statistic (rather than Story Points, as shown in the screenshot above).