This page refers to the advanced planning features that only available as part of Jira Software Cloud Premium and Enterprise.
We have a separate section for documentation about the project timeline that’s included in all Jira Software projects. Go to the documentation for project-level roadmaps in Jira Software.
The Progress (story points or days) column shows the completion percentage of your project based on the estimated values of issues versus the amount of completed work. It also includes a breakdown of Estimated and Unestimated issues, the latter of which which may impact the accuracy of your progress. These numbers include issues that are hidden from your current plan view using filters.
If you've enabled rolled-up values in a plan, you may see inconsistent values between rolled-up estimates of a parent issue and the values in the progress bar. Learn how roll-ups work in your plan.
To get a more detailed breakdown, hover on the progress bar to show a flyout window:
You can also track progress from the Summary tab on the left side navigation. Learn more about the Summary page.