Change the work type for multiple work items

You can change the work type of multiple work items at once.

You need to have the relevant space permissions to change work types.

More about project permissions

Change the work type of multiple work items from the backlog

You can only change the work type of multiple work items from the backlog if you’re in a software space.

To change the work type of multiple work items from the backlog:

  1. Select multiple work items from the backlog. You can either:

    1. use the work item checkboxes

    2. hold Ctrl (Windows) or Command (Mac) while selecting work items

    3. hold the Shift key to select a group of adjacent work items

  2. Select More actions (•••) on one of the selected work items, then select Bulk change.

  3. Select Move work items and select Next.

  4. Select the same destination space, choose a new work type, and select Next.

  5. Select a value for any required fields for this move, and if available, decide whether you'd like to send email notifications. Select Next.

  6. Review your changes and select Confirm, then Acknowledge.

Change the work type of multiple work items from the board

You can only change the work type of multiple work items from the board if you’re in a software space.

To change the work type of multiple work items from the board:

  1. Select multiple work items from the board. You can either:

    1. hold Ctrl (Windows) or Command (Mac) while selecting work items

    2. hold the Shift key to select a group of adjacent work items

  2. Right-click or select More actions (•••) on one of the selected work items, then select Bulk change.

  3. Select Move work items and select Next.

  4. Select the same destination space, choose a new work type, and select Next.

  5. Select a value for any required fields for this move, and if available, decide whether you'd like to send email notifications. Select Next.

  6. Review your changes and select Confirm, then Acknowledge.

Change the work type of multiple work items from the work item navigator

To change the work type of multiple work items from the All work view:

  1. From your space navigation, select All work.

  2. Adjust the search criteria to show the appropriate list of work items.

  3. Select More actions (•••) and choose Bulk change work items.

  4. Select the work items you'd like to perform the bulk operation on, and select Next.

  5. Select Move work items and select Next.

  6. Select the same destination space, choose a new work type, and select Next.

  7. Select a value for any required fields for this move, and if available, decide whether you'd like to send email notifications. Select Next.

  8. Review your changes and select Confirm.

We’re merging the All work view with the List. If you can’t see All work in your space navigation, you’re already viewing the new List experience. The features described on this page are relevant for both experiences. Read more about the merge

Still need help?