Start, edit, and complete a sprint*
Select Projects in the tab bar, and open a project.
Select the Backlog project tab.
Select ••• (more) next to the sprint’s name. This will reveal sprint actions, including Complete sprint.
Complete an active sprint*
If a sprint has started, you can complete it in two different ways:
Select Projects in the tab bar, and open a project.
Go to the Backlog project tab.
Select ••• (more) next to the sprint’s name, and select Complete sprint.
OR
Select Projects in the tab bar, and open a project.
Go to the Board project tab.
Select the board’s ••• (more) icon near the top of your screen, and select Complete sprint.
Delete an inactive sprint
If a sprint hasn’t started yet, you can delete it:
Select Projects in the tab bar, and open a project.
Go to the Backlog project tab.
Select ••• (more) next to the sprint’s name, and select Delete sprint.