Remaining hours and Due Date auto populated when linking dependencies

Platform Notice: Data Center Only - This article only applies to Atlassian products on the Data Center platform.

Note that this KB was created for the Data Center version of the product. Data Center KBs for non-Data-Center-specific features may also work for Server versions of the product, however they have not been tested. Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.

*Except Fisheye and Crucible

Summary

Problem

When linking dependencies of upstream or downstream between stories, 1 day and due date is automatically populated.

(Auto-migrated image: description temporarily unavailable)

Diagnosis

Client is using BigPicture - for ppm, project management for resource management

Cause

This is default behavior in BigPicture - for ppm, project management when synchronizing with JIRA.

Solution

Workaround

Ensure that all settings are configured for the BigPicture Gantt configuration, and Task period configuration is no synchonizing.

  1. Go to ⚙ > System > BigPicture > Gantt configuration

  2. Ensure all fields are completed

  3. Turn off 'Task period configuration'

Updated on April 8, 2025