Advanced Roadmaps Plan shows incorrect start date for sprints
Platform Notice: Cloud and Data Center - This article applies equally to both cloud and data center platforms.
Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.
*Except Fisheye and Crucible
Summary
The Sprint Start Date in an advanced roadmaps for Jira plan is showing one day prior to the actual start date of the sprint.
Diagnosis
Check your timezone in Jira.
For example, let's imagine Jira uses the IST timezone and your sprint start time is set as 12:30 a.m. IST is equivalent to UTC +5:30. Therefore, the time displayed on plans would be UTC = IST - 5:30 a.m., which is shown as the previous day.
Cause
As for all dates in Advanced Roadmaps, sprint dates are converted to their UTC (Coordinated Universal Time) equivalent.
Solution
Set the sprint start time to account for the UTC differential
To overcome this, select a sprint start date of 5:30 a.m. when your timezone is IST hours. For other time zones, follow the equivalent math to ensure that a conversion to UTC doesn't change the sprint start date.