Note that this KB was created for the Data Center version of the product. Data Center KBs for non-Data-Center-specific features may also work for Server versions of the product, however they have not been tested. Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.

*Except Fisheye and Crucible

Summary

Problem

The planning horizon has been configured to one default value which is 5 years. However, using Dark features the planning horizon can be configured to 30 years as well.

Note: Planning horizon can only be configured to 5 OR 30 years only.

Solution

  1. Login as an administrator and go to [your-instance-name]/secure/SiteDarkFeatures!default.jspa

  2. In the Enable Dark Feature text field add the following and then click on "Add". This will automatically configure the Planning Horizon to 30 years.

    1 com.atlassian.portfolio.scheduling.UnlimitedPlanningHorizon

    Note: These dark features are enabled for all users and cannot be disabled other than via this screen.

    ℹ️ This will automatically configure the Planning Horizon to 30 years.