Entering and Exiting Daylight Saving (DST) in JIRA

Platform Notice: Data Center Only - This article only applies to Atlassian products on the Data Center platform.

Note that this KB was created for the Data Center version of the product. Data Center KBs for non-Data-Center-specific features may also work for Server versions of the product, however they have not been tested. Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.

*Except Fisheye and Crucible

Summary

This page is to explain what happens to the Date Time field values when entering and/or exiting DST in JIRA.

Solution

Example

Assume Sydney is entering DST on October 4th 2015 02:00. At this time, Australia/Sydney time will shift forward an hour, becoming October 4th 2015 03:00.

  • The created date value for issue ABC-678 is 1/Oct/15 9:42 PM, and will remain as is.

  • A new issue ABC-679 created after 4/Oct/15 3:00 AM will use the current (DST) time for its created date.

Answers

  • The existing values in Date Time field and Date/Time history will remain unchanged.

  • The Date Time field and Date/Time history for events scheduled after Daylight Savings Time begins will reflect the new updated timezone.

  • ℹ️ Ensure Java is updated to the latest version supported by your version of Jira. Please refer to the JIRA Supported Platforms page for more information (Select your correct Jira version at the top-right).

Updated on April 8, 2025

Still need help?

The Atlassian Community is here for you.