During a JIRA Evaluation or Early Implementation, CPU Spikes Due to Running on VMWare

Platform Notice: Data Center Only - This article only applies to Atlassian products on the Data Center platform.

Note that this KB was created for the Data Center version of the product. Data Center KBs for non-Data-Center-specific features may also work for Server versions of the product, however they have not been tested. Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.

*Except Fisheye and Crucible

Symptoms

Intermittently, CPU will spike to 100% during normal JIRA operations. Performance is occasionally degraded, with no predictable pattern. This can happen after a long time of successful operations, or immediately upon JIRA startup.

The title of the report suggests this can happen during an evaluation, because it's the most common reason for performance issues during the evaluation process. It in no way relates to the evaluation license, which is technically identical to production licenses.

Cause

Virtual environments such as VMWare can cause this.

Resolution

As of September, 2009, JIRA is now supported in Virtual environments. Please review Run Jira server in a virtualized environment for configuration tips.