Axis of Burndown Chart displaying irregular dates
Platform Notice: Cloud and Data Center - This article applies equally to both cloud and data center platforms.
Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.
*Except Fisheye and Crucible
Problem
The x-axis of the Burndown Chart (displaying the current active sprint) is displaying a date well into the future.

Cause
The x-axis of the Burndown Chart is dependent on the Start/End Date of that particular sprint


Resolution
Change the End Date of the Sprint to the desired value
Navigate to the Backlog (Plan mode) of the Board and you will see the Start/End date
Click on the date and choose the desired date
Updated on April 1, 2025
Was this helpful?
Still need help?
The Atlassian Community is here for you.