Summary

In Jira Align, the target sprints (start & completion) fields are not available within the details of features.

Environment

Jira Align

Solution

Check the configuration of the details panel for the features using these steps:

  1. Navigate to Jira Align > Settings / Administration > Details Panels Settings

  2. Select the desired Portfolio

  3. Select Work Item = Feature (Jira Epic)

  4. Turn ON the toggles for

    1. Target Completion Sprint

    2. Target Start Sprint

  5. When reviewing the details of features make sure that +Full Details has been expanded

ℹ️ Side notes:

  • The above toggles are enabled per Portfolio.

  • If checking the settings make sure the correct Portfolio is chosen in Step 2