Roadmap Progress Calculation in Jira Align

Platform Notice: Cloud and Data Center - This article applies equally to both cloud and data center platforms.

Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.

*Except Fisheye and Crucible

Summary

What formula is used for the calculation of Roadmap % complete?

Environment

Jira Align

Solution

What formula is used for the calculation of Roadmap % complete?

If a work item is in a final state (state 5 for Feature, state 3 for Theme, Epic, capability), we have 100% complete.If a work item is not in a final state, and Total Points = 0, then 0%.If not in 1st or 2nd, then Total Accepted Points/Total Points*100.

Should the Roadmap % complete change with top-tier options?

Roadmap results depend on Tier1 selection. When some work items do not correspond with Tier1 selection, those work items are not included in calculations.

Should the % complete on Roadmap match the % complete on individual Epic when opened with the details panel?

Epic can be assigned to multiple programs and PIs. In Epic’s slide out there is general info for that specific Epic and total amount of work items and story points for all assigned programs and PIs. For Roadmaps, Tier1 selection can’t be multiple programs/solutions/portfolios. Even if a few org structures are in Tier1, Roadmap displays results only for the first one.

Updated on April 14, 2025