Summary

When a new portfolio is created in JiraAlign, upon trying to access it from the top Portfolio navigation menu ends up with the below error

(Auto-migrated image: description temporarily unavailable)

Solution

In order to fix the above error, it is important to associate the Portfolio with at least 1 Program.

As soon as a Program is associated with the new Portfolio, it will start loading the Portfolio details upon accessing from the top Portfolio menu