Feature Progress shows 100% but child Stories are still pending in Jira Align

Platform Notice: Cloud and Data Center - This article applies equally to both cloud and data center platforms.

Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.

*Except Fisheye and Crucible

Summary

The Feature progress bar in the Program Room is showing 100% completion even though child Stories are still pending.

Environment

Jira Align

Diagnosis

The progress bar shows 100% complete, however, the status is still in progress. In the following example, there are 5 underlying stories. Of those 5, one has been accepted and 4 are still pending.

(Auto-migrated image: description temporarily unavailable)

Cause

The Progress Bar is determined by the LOE points outstanding. If there are Stories that are not Accepted, but have zero LOE points, then they don't count towards the Progress Bar calculations.

Solution

Check if any of the child Stories that are not Accepted have zero LOE points.

Updated on April 14, 2025