Why I can't complete my sprint

Platform Notice: Cloud Only - This article only applies to Atlassian products on the cloud platform.

Summary

(Auto-migrated image: description temporarily unavailable)

You are unable to complete a sprint in your project.

Environment

Atlassian Jira Cloud

Diagnosis

This can happen :

  • If the same Sprint appears on two different Scrum boards.

  • A sprint shows up on a board in which it wasn't created.

  • Making a change to a sprint in one board affects a sprint in another board.

  • Attempting to complete the sprint requires admin permissions in another project.

(Auto-migrated image: description temporarily unavailable)
(Auto-migrated image: description temporarily unavailable)

In the screenshots above, Sprint name "Sprint 1 Project1" appears in two different projects under two different Scrum Boards.

Cause

Sprints aren't dependent on a specific board or project. It's, therefore, possible for a sprint to be displayed on more than one board. It is still one entity though, and changes made to it in one board will be reflected in the other as well. Furthermore, if an issue was modified or moved and as a result, is displayed in a new board, the sprints that it was originally assigned to will be shown in that new board too. Now, if you intend to complete thesprint you would need "Manage Sprints permissions" in all of the projects.

Solution

However, if you don't have admin permission for other projects, you can create a new sprint in one of the projects and bulk change the Sprint field on all of the relevant issues. This way you can move all relevant issues to the new sprint and be able to complete the sprint without issues.

Updated on April 8, 2025