Jira DC Advanced Roadmaps: 'Unresolved Issue After End Date' Warning in Plans

Platform Notice: Data Center Only - This article only applies to Atlassian products on the Data Center platform.

Note that this KB was created for the Data Center version of the product. Data Center KBs for non-Data-Center-specific features may also work for Server versions of the product, however they have not been tested. Support for Server* products ended on February 15th 2024. If you are running a Server product, you can visit the Atlassian Server end of support announcement to review your migration options.

*Except Fisheye and Crucible

Summary

An incorrect status category can cause the warning below next to resolved issues in plans:

Unresolved issue after end date This issue is still unresolved after the target end date. Check if the status needs updating, or if more time is needed for the issue.

Advanced Roadmap Plan View with warning triangles next to some entries. Selecting the warning will show the text "unresolved issue after end date" although the displayed status is called DONE

Diagnosis

As a Jira user

  • Open the ticket in the View Issue page

  • Note that the status has a Blue colour, even though the issue is resolved (it has a resolution set).

  • In the example screenshots, we have used the status Done, but the same would apply for any other status, which should represent a ticket in its completed state.

View Issue page, displaying an example Bug in status DONE. The issue status is displayed in Blue, the resolution field has been set to DONE

Please contact your Jira Administrator for the next steps and solution.

As a Jira Admin user

  • Go to the page Administration ⚙ > Issues > Statuses

  • Check the Category column of the Status in question

Status page showing the category In Progress for the status DONE
  • If the Category is not set to Done but instead to To Do or In Progress, then this article is relevant

Cause

The warning shows in the Plan because the status is configured as an In Progress or To Do type status rather than a Done type status.

As a result, the Plan does not treat this status as a completed status and thinks that the work in the ticket has not been completed yet, ultimately adding a warning next to this ticket.

Please note that changing a status category will impact

Solution

To identify incorrect statuses in Jira, follow these steps:

  1. Log in as a Jira Admin User: You need administrative access to check and modify status configurations.

  2. Navigate to Statuses:

    • Go to the Jira settings by clicking on the gear icon (⚙).

    • Select Issues from the dropdown menu.

    • Click on Statuses.

  3. Check the Category Column:

    • Look at the Category column for each status.

    • Identify statuses that are incorrectly categorized. For example, if a status that should indicate completion (like Done) is categorized under To Do or In Progress, it is incorrect.

  4. Correct the Category:

    • Change the category of the status to Done if it represents a completed state.

By following these steps, you can ensure that statuses are correctly categorized, which helps in avoiding warnings like "Unresolved issue after end date" in Jira plans.